Step-by-step Overview
The following flowchart gives an overview of the process that needs to be undertaken in developing an alternative waste treatment facility. Key elements are listed for each step and indicative timeframes are outlined.
Indicative timeframe: 36 - 72 months
Start here
STEP 1
STEP 2
Technical options analysis
- Waste characterisation study
- Technology options screening process
Service delivery options
- Identify if project falls under municipal service or function
- Determine risk retain and transfer
- Consider MSA
Council resolution
Approval to proceed to feasibility
STEP 3
Feasibility
- Appoint service provider to determine technical, financial, economic and environmental feasibility
- If PPP (s120) follow National Treasury PPP directives
Council resolution
Approval of feasibility to continue to procurement process
STEP 4
Procurement process
- Bid specification
- Bid evaluation
- Bid adjudication
- Special procurement procedures for PPP
- Formulate contracts
- Contract negotiation
- Contract finalisation
Contract management and commence construction
- Comply with contractual agreements throughout construction phase
Monitoring and maintenance
- Consider Greenhouse gas emissions
- SAWIS: Capture routine data on the tonnages of waste generated, recycled and disposed on a monthly and annual basis
GHG Calculator